Sealbook

Scope creep

Scope creep in ERP and planning implementations starts in a meeting

PMI found that 52% of projects had scope creep or uncontrolled scope changes in 2018, up from 43% five years before. On implementations it rarely starts with a change request. It starts with a decision two people remember differently.

How it starts

An SAP, Dynamics, NetSuite, Anaplan or Pigment rollout runs on hundreds of small design decisions: which chart of accounts to migrate, how many approval levels, which driver for allocations, what is in release one. Most are made on calls. Each one is a place where the client's expectation and the build can drift apart.

The drift stays invisible until testing. Then it arrives as "this isn't what we agreed", and the firm faces a choice: argue, or rebuild for free. Either way the scope just grew, and nobody filed a change request.

Typical examples

  • "Twelve-month rolling average for release one" becomes "we always meant six months" at UAT.
  • "Vendors without a tax number don't migrate" was agreed by someone without the authority to agree it.
  • "Revenue share for IT, headcount for facilities" was reversed in the same meeting, and the recap captured the first version.

Stopping it at the source

  • Capture each design decision with the exact words from the call.
  • Get it confirmed by the client's named reviewer, on that wording, within days, not at UAT.
  • Lock it. Any later difference becomes a visible change request, which can be scoped, priced and approved.

That turns scope creep into scope change, which is the difference between losing margin and billing for it.

Source: PMI, Scope creep rising (Pulse of the Profession 2018). Examples are made up; they are the kinds of decisions in Sealbook's test meetings.